This week, taping went in over the screws in the wallboard. Texture will go on next. Next week, cabinets will start in the kitchen. On the exterior, the final coat of stucco will go in. The following week, interior doors are expected, as is casing on the windows.

Sean's projecting a February 15th move in now - a direct 1 month impact in his estimate due to the snafu on the rough inspection. Laura and I are still puzzling on that completion date. Once the cabinets, casings, doors are in, it seems there's painting and floors (both tile and wood) inside, painting and stone work on the outside, plus electrical fixtures in and out. We'll be asking about trades for each running in parallel, as it feels to us that crews for a couple at a time could be working without getting in each other's way.